HTML Preview Road Construction Project Progress Report page number 1.


ROAD CONSTRUCTION
PROJECT PROGRESS REPOR
T
Des. No.: Location:
ITEM ITEM VALU
E
PERCEN
T
PERCEN
T
Last Report This Report COMPLETE
Process Survey & Check Survey Notes 2.0
Design Preliminary Grade (Mainline H & V) 2.0
Mainline Culvert Hydraulic Analysis 2.0
Design Over-Pass S-Lines 1.0
Prepare Preliminary Title Sheet & Index Sheet 0.5
Prepare Prelim. Typical Cross Section 1.0
Overall plan view 0.5
Overall Proposed Profile Sheet 0.5
Interchange-Geometric Submission to FHWA 0.5
GRADE REVIEW MEETIN
G
10.0 0.0
Design Grade (Mainline, S-Lines, Driveways & Local Roads) 4.0
Preliminary Guardrail Design 1.5
Preliminary R/W Design 2.0
Preliminary Drainage Design 2.5
Preliminary Quantities & Cost Estimate 1.5
Preliminary Plan & Profile Sheet 1.0
Detail Sheets 1.0
Interchange Sheets 1.0
Preliminary Cross Section Sheets 0.5
STAGE 1 REVIEW SUBMISSION 25.0 0.0
Revise plans per Stage 1 Review 1.0
GEOTECHNICAL INVESTIGATIO
N
REQUEST SUBMITTA
L
26.0 0.0
Clear Zone / Roadside Safety Design 2.5
Prelim. Approach, Drive & Intersection Details 2.5
Prelim. Plat #1 or #3 1.5
Preliminary Maintenance of Traffic 3.0
Draft Wetland Mitigation & Flood Control Plan 2.0
Detail Sheets 0.5
Road Summary Sheet 0.5
Structure Data Sheet 0.5
Approach Table 0.5
Prel. Plot of Final Cross Sections 0.5
PRELIMINARY FIELD CHECK PLAN
S
40.0 0.0
Field Inspection 1.5
Revise Plans per Field Check Comments 1.0
Final R/W Design & Plans 1.5
Final R/W Plat #1 or #3 0.5
PRELIMINARY R/W PLANS SUBMITTA
L
44.5 0.0
Final Approach, Drive & Intersection Details 2.0
Construction Cost Estimate Update 1.0
Finalize Title Sheet for R/W Plans 0.5
Finalize Typical Cross Sections 1.0
Final Plan & Profile Sheets 2.5
Soil Boring Sheet 0.5
Wetland Mitigation & Flood Control Plan 1.0
Preliminary Approach Table 1.0
Final Cross Sections 1.0
STAGE 2 REVIEW SUBMISSION 55.0 0.0
STATUS REPORT