HTML Preview Sample Monthly Construction page number 1.


CONSULTANT’S MONTHLY PROGRESS REPORT: STANDARD FORMAT
SECTION SUB-SECTION DESCRIPTION
COVER SHEET
1 EXECUTIVE
SUMMARY
A one page summary, including
progress over the reporting
period, overall progress to date,
work completed/ in progress and
significant Contract events
occurring or in progress over the
reporting period
2 CONTRACT
PARTICULARS:
- Employer Name
- Consultant Name
- Contractor Name
- Commencement Date
- Original Completion Date
- Revised Completion Date
- Contract Amount
- Revised Contract Amount
- Defects Liability Period
- Financing Organisations
- General Layout Plan
3.1 Location Plan Location within Lebanon
3.2 Site Plan Showing names of villages, towns,
major structures and intersections
3.3 Description of the Works - Road classification, name and
number of lanes
- Description of major structures
- Number and type of other
structures
- Number of culverts
- Other significant features
3 PROJECT
DESCRIPTION
3.4 Financial Status A chart showing current and
forecast cash flow. Include
revisions arising from variations
and extensions of time
4.1 Progress During the
Reporting Period
A narrative, including
descriptions of delays and
percentage completion over the
reporting period
4 WORKS PROGRESS
4.2 Progress Status Since the
Start of Works
A narrative, including
descriptions of delays and
percentage completion since the
start of works
5.1 General Details of the Contractor’s
programme submittals
5.2 Works Progress vs
Programme
One A3 page copy of the
Contractor’s outline programme
of works in MS Project or
Primavera Format, including
progress to date
5 WORKS
PROGRAMME
5.3 Delays Description of delays and
estimate of time lost
DOWNLOAD HERE


If you see a bandwagon, it’s too late. | James Goldsmith