CONSTRUCTION MEETING AGENDA DATE: 6/14/11
ADMINISTRATIVE
Construction Meeting No.: 1
Project Name: Keystone Middle School
Meeting Location: Job site 1:30 P.M.
Attendees:
David J. Leach, The Cornice Company
Wes Stein, The Cornice Company
Mike DeLouise, The Cornice Company
Nick Baker, G.E. Baker Construction
Dennis Walter, Keystone Schools
Michael DiMaio, FMD Architects NP
Brandi Fry, FMD Architects
Jay Arbaugh, Keystone Superintendent
Michael Smith, Keystone Schools
I. GENERAL AGENDA
A. Contractors are responsible for items discussed in the meetings whether they are present or not. Project
Managers should be present at meetings.
B. Discuss Construction Schedule.
C. Safety – Please follow all OSHA guidelines.
D. Keep lines of communication from Contractor to Construction Manager to Architect
II. WORK PROPOSED FOR THE NEXT TWO WEEKS
G.E Baker
1. Earthwork
2. Utilities
3. Review the Headwall credit- will provide
III. SUBMITTALS
1. Returned Aggregate Submittal
2. Hand over Pre cast submittal E-mailed 6-9-2011 followed up 6-10 with phone call
IV. SCHEDULE
1. Job trailer to be delivered next Tuesday
2. Status of Pre Cast Delivery
3. Curb cuts and Silt Fence
4. Construction Drive
5. Full mobilization Monday
6. Survey for Sanitary complete
IV. ISSUES FOR DISCUSSION
A. New Business
V. COMMENTS
Architect –